Health Facilities

Helipad
Prince Georges' County Hospital

The project consisted of first evaluating the existing 9 story hospital. The existing structure is cast-in-place concrete.. The elevated helipad was to be placed above the existing penthouse roof level. The design was a 70'x70' steel framed with heated concrete deck. The design required the extension of 2 of the 3 existing elevator shafts and the relocation of the associated equipment. We also provided a new elevator lobby and walkway at the Helipad level and new elevator machine room.

Completion Date: 9/1998
Total Cost: $1,000,000.00
Work for which firm was/is responsible: $500,000.00